Friday, April 20, 2012

Farce called 'EIA Public Hearing' exposed yet again!


Dear Friends/Co-sailors,

Greetings from Water Initiatives Odisha (WIO) !

In yet another significant ruling, the National Green Tribunal (NGT) has today (20th April 2012) exposed the farce called EIA public hearings.  

The NGT has set aside the Environmental Clearance granted to the 4 MTPA Coal Mining Project of Jindal Steel and Power Ltd. (JSPL) and 4 MTPA Coal Washery at Gare IV/6 at Raigarh District, Chhatisgarh.  The major ground of this decision is the "faulty Public Hearing".  The judgment delivered by Justice C.V Ramulu and Prof Dr R. Nagandran held that the entire Public Hearing was a ‘farce’ and makes a ‘mockery’ of the public hearing process’. The Ministry of Environment and Forest in an illegal manner decided that the Public hearing was complete and granted the clearance. The Appeal against the Environmental Clearance was filed by Adivasi Kisan Mazdoor Kisan Ekta Sanghatan  through Harihar Patel and and Jan Chetna through Ramesh Aggarwal.   

Here below, we paste some important excerpts from the Judgment for your kind reference.  In our state, as has been pointed out by many concerned citizens and organisations time and again, most of the EIA public hearings are farcical and are stage managed shows to favour the companies.  This is high time the MoEF learns a lesson from this and reviews all the public hearings and cancel the ones which have been farcical. 

==============
Excerpts from the NGT Judgement dated 20th April 2012:

"......... In the case on hand, after viewing the CD of the public hearing conducted on 5.1.2008, we are surprised to note to our dismay that the same was a “farce”. It was a mockery of the public hearing and the procedure required to be followed thereof. All the norms required in conducting a smooth and fair procedure was given a go by.
For conducting Public Hearing, a big pedal was erected, and a dais was created, and in front of the dais some officers were made to sit, for recording the statements made by the participants. The area covering the dais and the place where the officers were sitting was safely cordoned and in front of them about 200 plastic chairs were arranged for the public. Even before the public hearing could start, the affected people raised slogans to stop the public hearing. However, on the intervention of the Additional District Magistrate a few persons came forward and gave their statements saying that no Gram Sabha was conducted and the Gram Panchayats have issued “No Objection Certificates” and such certificates are invalid and cannot be relied upon to say that the people in the village have no objection for acquiring their lands for establishing the project. It is also pointed out that none of the Sarpanches of the affected villages or other public representatives of the local bodies are present in the public hearing. Thereafter, the women from the affected villages who opposed the establishment of the project came in a queue one after the other and simply said that they oppose the project since their lands are being affected and their livelihood is taken away. The names of the persons and other details such as name of the father/husband, village and the extent of land and survey number were not recorded. The mike was not given to them and many of them were directly exposed to the video.

In the meanwhile, it appears the persons raising slogans against each other also pelted stones and that created some commotion which resulted in the intervention of the police and use of force. The participants however, broke all the plastic chairs and left the place. The officers were all sitting quietly even after the people left the place after the police used force. Some media persons and the local people objected for continuing the proceedings after the people left the place. In fact, there was no announcement that the proceedings would be resumed after some time. However, the Additional District Magistrate resumed and continued the proceedings in the presence of few persons. This time only the supporters of the project were paraded one after the other only to say one word “I Support”. The persons who supported the project all appeared to have been brought and prompted by the proponent. It was a mockery of the entire process of public hearing. At the end, the Additional District Magistrate, declared that the public hearing was complete and there was no necessity for the project proponent to answer anything since there was nothing much has been spoken by the persons opposing the project. Further, no summary of the public hearing was prepared in the local language nor it was made known to the public. The ADM abruptly declared that the proceedings are concluded. The way in which the proceedings are conducted is nauseating and no reasonable person would accept that it was conducted fairly and much less properly.

This is not a case where there are a few ignorable procedural lapses in conducing the public hearing.  This is a case of a mockery of public hearing, which is one of the essential parts of the decision making process, in the grant of Environmental Clearance.  this is a classic example of violation of the rules and the principles of natural justice to its brim.  Therefore we consider it appropriate to declare that the public hearing conducted in this case is nullity in the eye of law and therefore is invalid".....
============= 

Thanks and regards,

Ranjan

--
Ranjan K Panda
Convenor
Water Initiatives Odisha: Fighting water woes, combating climate change... more than two decades now!
INDIA

Mobile:             +919437050103      
You can also mail me at: ranjan.waterman@facebook.com

Skype: ranjan.climatecrusader


Please join our group 'Save Rivers Save Civilizations' at http://www.facebook.com/groups/220598744649462

Water talks to me, I speak for Water...

Saturday, April 7, 2012

Thought for 8th April 2012


Natural order of a relationship starts with trust rather than test…

Good Morning & have a Great Sunday!


Ranjan Panda

Friday, April 6, 2012

Thought for 7th April 2012


Diving into alien water is more comfortable than foraying into a strange society.  Water shows its true colours, humans hide…



Good Morning & a Great Weekend freinds!

Ranjan Panda

Thursday, April 5, 2012

Thought for 6th April 2012


Innumerable complex processes, taking a long time, bring you to existence.  You want to live still longer.  But you want to gallop the Earth tout de suite.  You are the Man(un)kind…


Good Morning and Good Friday!!
Ranjan Panda

Wednesday, April 4, 2012

Thought for 5th April 2012

Respecting others is not merely a matter of manner but that of an attitude.  Its a reflection of your character...


Ranjan Panda

Tuesday, April 3, 2012

Thought for 4th April 2012

Perfectionism is essentially a mind game.  Your search for perfection ends when your mind wants you to...




Ranjan Panda

Monday, April 2, 2012

Public Statement on SC order on Inter Linking of Rivers


Public Statement on Supreme Court order on Inter Linking of Rivers
PLEASE PUT THE ORDER ON HOLD AND RECONSIDER


Dear Sir/Madam,

Greetings from Water Initiatives Odisha!


A number of citizens have made a public statement, expressing serious concern about the Supreme Court’s Order of Feb 27, 2012 on the Interlinking of Rivers Project. The statementendorsed by more than 60 persons has respectfully urged the Supreme Court to put this order on hold and reconsider the matter.

The statement first states the concerns relating to the propriety of the apex court making this specific order, and then proceeds to state the concerns relating to the Project itself. The full statement which has also been endorsed by WIO is pasted below.

Thanks and regards,

Ranjan
================== 
29 March 2012

THE SUPREME COURT’S JUDGMENT ON THE RIVER-LINKING PROJECT: A STATEMENT AND AN APPEAL BY CONCERNED CITIZENS

We, the signatories to this statement, wish to record our utmost concern at the Hon’ble Supreme Court’s judgment of 27 February 2012 on the Inter-Linking of Rivers Project (ILR), on the following grounds:
(1) The judgment gives categorical directions to the Executive Government on a matter which is clearly in the executive domain, namely the implementation of a particular project.
(2) It gives the direction to implement the ‘project’, i.e., the grand design as a whole, at a time when none of the thirty projects that constitute that grand design has gone through the processes of examination, evaluation and approval and received final sanction. In fact, even the earlier stage of project formulation has not been completed in most cases; only three of the thirty projects have reached the Detailed Project Stage, and even these are not final.  
(3) By declaring the project to be in the national interest it not only anticipates the result of the examination that is yet to take place, but also makes it extremely difficult for the various governmental agencies and Ministries to undertake a rigorous and objective examination.
(4) Its reference to “the unanimous view of all experts” that the project is “in the national interest” is patently untrue, because there is a substantial body of expert opinion that is highly critical of the project. Such a serious error would not have occurred if there had been consultations with scholars of various disciplines who have given thought to the matter.
(5) It fails to take note of, or treats lightly, the strong dissent on the part of several State Governments.
(6) The following is a succinct statement of the case against the project:
 (i) Instead of starting from the identification of the needs of water-scarce areas and finding area-specific answers, the project starts by looking at a map of India, decides a priori that the rivers of India can and should be linked, and then proceeds to consider the modalities of doing so. This is a reckless and major redesigning of the geography of the country.
(ii) The related ideas of a ‘national water grid’ or the ‘networking of rivers’ give evidence of profoundly wrong thinking about rivers. Rivers are not pipelines.
(iii) The grand design consisting of 30 projects involving upwards of 80 dams is bound to have major environmental/ecological consequences, which might even be disastrous in some cases. Each dam will also mean the displacement of people to varying extents, and may cause injustice and hardship.
(iv) The Project is at variance with the growing recognition that it is necessary to move away from the long-standing engineering tradition of a supply-side response to a projected or imagined demand, and towards restraining the growth of competitive unsustainable demand for water in all uses.
(v) Assuming that some augmentation of supply is necessary, the project fails to consider alternative possibilities, of which there are several very good examples.
(vi) The idea of transferring flood waters to arid or drought-prone areas is flawed because (a) there will be hardly any flood-moderation; and (b) this project will be of no use at all to the drylands and uplands of the country.
 (vii) The idea of transferring water from surplus to deficit basins is equally flawed because the very notions of ‘surplus’ and ‘deficit’ are highly problematic. The idea of a ‘surplus’ river ignores the multiple purposes that it serves as it flows and joins the sea, and that of a ‘deficit’ river is based on ‘demands’ on its waters derived from wasteful uses of water.
(viii) Careful, economical, conflict-free and sustainable intra-basin management should come first, and bringing water from elsewhere should be the last recourse.
 (ix) The project holds the potential of generating new conflicts between basins.
(x) There are international dimensions to this project. Both Nepal and Bangladesh have expressed serious apprehensions that need to be taken into account.
Having regard to the points made above, we, the undersigned, would earnestly and respectfully urge the Hon’ble Supreme Court to put the judgment on hold and undertake a careful reconsideration of the entire matter. We would also respectfully suggest a study of the available literature on the subject, and consultations with several distinguished critics of the project.

Some of the signatories to this Statement include: Ramaswami R Iyer, Prashant Bhusan, Himanshu Thakkar, Manoj Mishra, A. Latha, Indira Khurana, Dinesh Kumar Mishra, Vandana Shiva, Ranjan Panda...


-- 
Ranjan K Panda

Convenor

Water Initiatives Odisha: Fighting water woes, combating climate change... more than two decades now!

BASERA, R-3/A-4, J. M. Colony, Budharaja, Sambalpur 768 004

Mobile:             +919437050103      
Email: ranjanpanda@gmail.com, ranjanpanda@yahoo.com
You can also mail me at: ranjan.waterman@facebook.com

Skype: ranjan.climatecrusader


Please join our group 'Save Rivers Save Civilizations' at http://www.facebook.com/groups/220598744649462

Water talks to me, I speak for Water...
Water Initiatives Odisha (WIO) is a state level coalition of civil society organisations, farmers, academia, media and other concerned, which has been working on water, environment and climate change issues in the state for more than two decades now.